The One to Count On...

High School Construction Update

Posted: Thursday, January 13th, 2011 at 6:30 am
Author: KCII News - Bill Gatchel

[simage=1104,400,n,center]

Washington’s new high school is on schedule.  Project Coordinator Dan Culp says the steel construction at the new high school is scheduled to start today or tomorrow.  He also says plumbing on the project is completed for the entire site except for the kitchen area.  Culp says as soon as the steel frame has been built, they will finish the plumbing.  He adds they have drilled 45 geothermal wells and plan in being finished drilling by the end of January or the first week of February.  The next construction update will be shared at the next school board meeting in February.