The Kalona City Council went over their 2012 street projects at this weeks meeting. City Administrator Ryan Schlabaugh shares that there are 6 projects and one alternate. The next step is bid letting. The City will take two bids one for the concrete and one for the asphalt. The estimate for the projects is $392,000. Schlabaugh says they’ll start the projects later this year, around late August early September.

Street Projects 2012

A Avenue by City Shop, concrete is to be put in due to the high level of traffic

13th St cul-de-sac in the north part of town

9th Street will be paved with asphalt from K to M Street and connecting 9th and 10th Street

A small section between 4th and 5th St on H Avenue

Section between 9th and 10th on D Avenue

Alternate: Section by proposed mini park on 3rd St from B to C Avenue, to be done after park is completed