Highway 1 Roadwork on Schedule

Posted: Tuesday, July 15th, 2014 at 6:22 am
Author: KCII News - Nathan Swenson

The construction on Highway 1 is on schedule. The road is being resurfaced from Washington to Kalona by Norse Asphalt and from Kalona to Iowa City by LL Pelling.

Iowa DOT Construction Technician Supervisor Marv May says if work isn’t delayed, the project from Washington to Kalona should be done by the end of this month. He predicts crews will be wrapping up the other roadwork by late August.

Motorists should expect alternating lane closures from a half hour after sunrise until a half hour before sunset Monday through Saturday due to the resurfacing.