Ainsworth residents are under another boil order, it’s the second time there has been a water main break in two weeks.

John Hazelett, Ainsworth’s water superintendent says the breaks are being caused by the waster main project underway in the city. He says during the effort to connect to the line air gets into the system which can cause a break.

Hazelett says the biggest part of the project could be finished in the next couple of weeks. He says he wouldn’t be surprised if there were further breaks before the project is finished, adding he expects things to settle down when the largest part of the water main project is finished.

He says overall the water system in Ainsworth is in good shape and the recent breaks are solely due to the water main project.