The Riverside City Council will meet Monday to discuss multiple city projects, including their 4th Street project. Construction began in early May with a total cost of $875,061.25. J&L Construction is working to replace the water mains, resurface the street, and add new curbs, gutters, storm drains, and sidewalks. The council looks to pay for another portion of work done from June 8 to July 10, costing $174,401.23 and representing 45% completion of the project. Crews anticipate work on this project to be finished by August 17. The city council meeting will begin at 6 p.m. at the Riverside Fire Station.